Public Works - Approve Change Order #2 (Final) with Asphalt Paving & Supply, Inc.in the decreased amount of $154,167.21 for Overlay (Western, FY 2016-2017) in Yavapai County, AZ - Project #1619215  (District 1 - Supervisor Simmons; District 2 - Supervisor Thurman; District 5 - Supervisor Smith)
Brief Explanation of Need
This county-wide overlay project has been completed. Actual field quantities resulted in a decrease of $154,167.21, bringing the final project cost to $1,303,555.26.  We respectfully request the Board of Supervisors approve the attached Change Order #2 (Final) with Asphalt Paving & Supply, Inc. so that the contractor may receive final payment and the project closed.
Presenter
Byron Jaspers, Public Works Director
Source of Revenue
HURF and Regional Roads
Have Notice/Publication Requirements Been Met
N.A
Contract or Agreement
N/A
Legal Approval Notes
N/A

Fiscal Impact
Total Cost: ($154,167.21)
Source of Revenue: See below
Name of Account to be Paid From: See below
Number of Account to be Paid From: See below
Was this item budgeted for: See below
Fiscal Impact:
HURF - 0201070230 77001CR0003 : - $116,285.53

Regional Roads - (0227) RR0145: - $37,881.68
Attachments
co#2 with AP&S

  
Legal Approval: No- Elected Official/Director has reviewed the attached agreement/contract
and determined legal review is not a requirement, or not applicable

AgendaQuick©2005 - 2017 Destiny Software Inc., All Rights Reserved