    24.    
BOARD OF SUPERVISORS AGENDA-2018
Meeting Date: 11/07/2018  
Submitted For: MaryAn Sala
Department: Public Works  

Action Requested
Public Works - Approve Change Order #1 (Final) in the decreased amount of $26,881.74 with Copperstate Paving & Construction, LLC for Lake Fork - Granite Gardens Road Improvement in Yavapai County, AZ - Project #1722061. YC Contract No. 2018-113A1 (District 4 - Supervisor Brown)
Brief Explanation of Need
The original contract price with Copperstate Paving & Construction, LLC for Lake Fork - Granite Gardens Road Improvement Project #1722061 was $189,724.83. After final quantities were calculated, this project was completed under budget in the decreased amount of $26,881.74. The final contract price is $162,843.09.

We therefore request the Board of Supervisors approve this final change order in the decreased amount of $26,881.74 so that this project may be closed.
 
Presenter
Dan Cherry, Public Works Director
Source of Revenue
HURF
Have Notice/Publication Requirements Been Met
N/A
Contract or Agreement
N/A
Legal Approval Notes
N/A

Fiscal Impact
Total Cost: ($26,881.74)
Source of Revenue: HURF
Name of Account to be Paid From: Construction in Progress
Number of Account to be Paid From: 0201070230 77001 1722061
Was this item budgeted for: N/A
Fiscal Impact:
Attachments
Change Order #1 (Final) with Copperstate - YC Contract No. 2018-113A1

  
Legal Approval: Yes- Legal Counsel has reviewed the attached agreement/contract
and has found it to be in proper form