Print Back to Calendar Return
    16.    
BOARD OF SUPERVISORS AGENDA-2018
Meeting Date: 11/07/2018  
Submitted For: Dan Cherry
Department: Public Works  

Action Requested
Public Works - Approve the addition of Reynolds Rd. and School House Gulch Rd. to the Public Works FY 18-19 Road Upgrade List. To be paid from existing HURF budgeted funds. (District 2 - Supervisor Thurman; District 5 - Supervisor Smith)
Brief Explanation of Need
Each year the Roads Division programs minor upgrades to county roads. Accordingly, the Division would like to add the following roads (with cost estimates) to the Public Works FY 18-19 Road Upgrade List as dirt to black paving projects which are carry-over projects from prior years that weren't finished in prior fiscal years due to varying circumstances:
Reynolds Rd, Black Canyon City, District 2 - $27,900.00
School House Gulch Rd, Groom Creek, District 5 - $71,700.00

We respectfully request the Yavapai County Board of Supervisors approval of the addition of these two roads to the Public Works FY 18-19 Road Upgrade List. The total cost is estimated at $99,600.00 to be paid from existing HURF budgeted funds.
Presenter
Dan Cherry, Public Works Director
Source of Revenue
HURF
Have Notice/Publication Requirements Been Met
N/A
Contract or Agreement
N/A
Legal Approval Notes

Fiscal Impact
Total Cost: $99,600.00
Source of Revenue: HURF
Name of Account to be Paid From: Construction in Progress
Number of Account to be Paid From: 0201070230 77001
Was this item budgeted for: No
Fiscal Impact:
Attachments
Reynolds Rd Map
School House Gulch Rd Map

  
Legal Approval: No- Elected Official/Director has reviewed the attached agreement/contract
and determined legal review is not a requirement, or not applicable

AgendaQuick©2005 - 2019 Destiny Software Inc., All Rights Reserved