Public Works - Approve Authorization of Services #1822872 with Ninyo & Moore in the amount not to exceed $7,186.00 for geotechnical services on the Bagdad Airport Restroom/Terminal Building project.  YC Contract No. 2019-005  (District 1 - Supervisor Simmons)
Brief Explanation of Need
Yavapai County is responsible for geotechnical and materials testing of the Bagdad Airport Restroom/Terminal Building Project.  Ninyo & Moore has been chosen to perform the testing associated with this project, and has submitted a quote for the work in the amount of $7,186.00.  This project is funded by ADOT Aeronautics Grant No. E5S1W at 95 percent and Yavapai County at 5 percent. Therefore, the Public Works Department requests the Yavapai County Board of Supervisors approve Authorization of Services #1822872 with Ninyo & Moore.
Presenter
Dan Cherry, Public Works Director
Source of Revenue
ADOT/Yavapai County General Fund
Have Notice/Publication Requirements Been Met
Contract or Agreement
Legal Approval Notes

Fiscal Impact
Total Cost: $7,186.00
Source of Revenue: ADOT/General Fund
Name of Account to be Paid From: Bagdad Airport Grant Fund
Number of Account to be Paid From: 0424070590 77001 AE5S1W
Was this item budgeted for: Yes
Fiscal Impact:
ADOT 95% - $6,826.70
YC (5%) - $359.30
Total - $7,186.00
Attachments
AOS#1822872 Ninyo & Moore
Current Contract Extension with Ninyo & Moore

  
Legal Approval: Yes- Legal Counsel has reviewed the attached agreement/contract
and has found it to be in proper form

AgendaQuick©2005 - 2019 Destiny Software Inc., All Rights Reserved